What evidence should a contractor provide before a defect is closed?

When a contractor reports a repair complete after handover, your customer care team still has to decide whether the case can close. This guide shows what to check, with three fictional evidence packs and a record you can copy.

Short answer

A contractor's completion report says the work is done; the evidence lets your care team check it. A useful pack identifies the case and location, restates the agreed work, describes what was actually done, includes the supporting material the work calls for and lists anything outstanding. The reviewer then records a decision. How much evidence you need depends on the work and its risk: a photo can show a replaced cupboard front, but rarely shows that the source of a recurring problem has been dealt with.

Start with the report and agreed work

Review the evidence against what was asked, not against how good the result looks. A sharp photo of a freshly painted wall answers nothing if nobody wrote down whether the job was to repaint the wall or to find out why a mark keeps coming back.

Before opening the contractor's photos, put four things side by side:

  • The original observation: what the owner reported, in their words, with the home, room and location.
  • The assessed work: what your team or the contractor decided needed doing after looking at it.
  • Any change to that scope: extra work found on site, work dropped or a different repair agreed, and who agreed it.
  • The review question: the one thing the evidence has to show, such as “the damaged front has been replaced” or “the source of the mark has been identified and dealt with”.

If you cannot write the review question in one sentence, the scope was not clear enough, and the first step is to clarify it with the contractor. The aftercare process guide places this review as the last step before closure; in the defect register template it is the Ready for review stage.

Ask for evidence that answers the review question

Ask the contractor for the material that answers your review question, grouped so the reviewer can find it. The record later in this guide uses six groups.

Six review areas
Review areaWhat it records
Identity and scopeCase reference, home and location; original observation; agreed work; relevant scope changes.
Reported completionWho reported the work complete and when; what was actually done; materials or documents that matter to the decision.
Supporting materialPhotos where they help, with file references and who supplied them; any inspection or test records the work requires.
Outstanding itemsUnfinished work, limitations the contractor reports, further assessment needed and the owner's own observations.
ReviewWho reviewed and when; what was looked at; what it supports; what is still uncertain; the decision and its reason.
Next stepFurther work or information; who is responsible and by when; how the owner was told; any related follow-up case.

What photographs can establish

Photos are good at showing visible condition and context. A wide shot shows which home and room you are looking at; a close-up shows the detail. Together they can establish that:

  • the work was carried out in the right home and location;
  • a visible part was replaced, refitted or refinished;
  • the surrounding area was left clean and undamaged.

Ask for each photo to carry the case reference in its file name or caption, so it cannot be mistaken for another home's. A photo cannot show how a door closes, what is behind a surface or whether a problem will return.

When other evidence is needed

Some work needs evidence that a photo cannot give: a written description of what was found, a record of an inspection or test, a manufacturer's document or an assessment by a qualified person. Which of these applies depends on the work and its risk, and that is a technical question. Ask the contractor, or a qualified person your team relies on, what would show that this particular repair is complete.

The checklist structures your review. It does not certify that work is safe or technically sound, and it does not replace the assessment a qualified professional would make.

Compare three completion packs

The same kind of evidence can support different decisions, depending on what the work was meant to achieve. The three packs below are fictional. Each shows what a reviewer could and could not conclude.

Three fictional completion packs
PackEvidence availableEvidence missingDecision it supportsNext action
A: cupboard-front replacementCase reference, the requested replacement, a dated description of the work, and a wide and a close-up photo, both labelledWhether the door now closes properly, which the owner raised before the visitThe front was replaced as asked; the closing concern is still openAsk the contractor whether closing was checked and confirm with the owner
B: unlabelled close-upOne close-up of a tile joint and a note saying “done”Home and location, the work carried out, a wider viewNone yet: the photo could belong to several homesRequest the case reference, a description of the work and a photo showing the location
C: recurring damp markOne photo of a repainted wallAny record of how the source of the mark was assessed or dealt with, which was the agreed workThe finish was renewed; nothing shows the agreed work was doneKeep the case open and ask a qualified person what evidence the work needs

Packs A and C both rely on an after-photo. For A, the photo answers most of the review question, because the request was to replace something visible. For C, it answers almost none of it: the agreed work concerned the source of the mark, and fresh paint shows only the surface. Pack B is a documentation gap, not a judgement on the contractor. It simply cannot be matched to a case yet.

Fictional example

A repainted wall, reviewed against the agreed work

EX-C03

Example development · Apartment 7 · Bedroom, below the window

Report and agreed work

  1. 2 OctOwner reports a dark mark below the bedroom window that has returned after cleaning
  2. 6 OctTeam asks the contractor to find and address the source of the mark, then make good the finish

Reported completion

  1. 20 OctContractor reports the job complete and sends one photo of the repainted wall

Review

  1. 22 OctReviewer finds no record of how the source was assessed; the photo shows only the finish
  2. 22 OctCase stays open; team asks a qualified person what evidence would show the source has been dealt with and tells the owner why

Fictional example. It shows a review decision only; it does not diagnose the mark or suggest a repair method.

Record the review and remaining uncertainty

Record the review as its own event, separate from the contractor's completion report. The report says what the contractor did. The review says what your team checked, what that supports and what it decided.

Four review decisions
DecisionWhen it fitsWhat to record
Close the caseThe evidence answers the review question and nothing agreed is outstandingReviewer, date, the evidence looked at and the outcome
Request informationThe work may be done, but the evidence cannot show itExactly what is missing, who will provide it and by when
Return for further workThe evidence shows agreed work is unfinished or not as agreedWhat remains, the new next action and its deadline
Obtain specialist reviewThe question needs technical judgement your team cannot giveThe question asked, who will answer it and what happens meanwhile

Write down the limits as well as the decision. “Front replaced; closing not checked” tells the next person far more than a ticked box. Then tell the owner the outcome; the guide to updating a homeowner when the repair date is unknown covers updates while work is still open.

Example request for missing information (pack B)

Thank you for the photo marked “done”. We cannot yet match it to a case. Please send the case reference, a short description of the work you carried out and a wider photo showing where the tile is. We will review it as soon as these arrive.

Evidence-review record

Copy these columns into your spreadsheet or the review notes of your existing system, one row per completion report. Fill in the first nine columns from the report and the case, and the last six when you review it. The rows show the three fictional packs from this guide.

Case and locationOriginal observationAgreed work and changesReported by and dateWork reported as doneSupporting materialInspection or test recordsOutstanding itemsOwner's observationsReviewer and dateWhat the evidence supportsRemaining uncertaintyDecision and reasonNext step, who, by when and related caseOwner informed
EX-A01 · Apartment 3 · Kitchen, cupboard left of the sinkCupboard front swollen at the lower edgeReplace the cupboard frontJoinery contractor, 14 Oct 2026Front replaced; hinges adjustedWide and close-up photo, both named EX-A01; supplied by the contractorNone suppliedNone statedOn 9 Oct the owner said the door catches when closingM. K., 15 Oct 2026The front was replaced in the right placePhotos cannot show whether the door still catchesRequest information: closing not confirmedContractor to confirm by 17 Oct; M. K. checks with the owner15 Oct: front replaced, closing being checked
EX-B02 · Apartment 11 · Bathroom, beside the shower trayLoose tile edgeRefix or replace the loose tileTiling contractor, 16 Oct 2026“Done”One unnamed close-up of a tile joint; no wider viewNone suppliedNone statedNone received yetM. K., 17 Oct 2026Nothing case-specific: the photo could belong to several homesWhich home and tile, and what work was doneRequest information: identity and scope missingContractor to resubmit by 20 Oct; M. K. reviews on receipt17 Oct: work is being checked, update by 21 Oct
EX-C03 · Apartment 7 · Bedroom, below the windowDark mark that returned after cleaningFind and address the source of the mark, then make good the finishContractor, 20 Oct 2026Wall repaintedOne photo of the repainted wallNo assessment of the source recordedWork on the source not describedThe mark has come back beforeM. K., 22 Oct 2026The finish was renewedWhether the source was found or dealt withObtain specialist review; case stays openQualified person to say what evidence is needed; M. K. by 29 Oct22 Oct: case stays open, reason explained

Scroll sideways to see every column.

Download the record (CSV)Opens in Excel, Numbers or Google Sheets. The example rows are fictional; delete them before use.

This record is a proposed working aid, not a technical standard or a legal test. Add the columns your contract or warranty process requires.

Handle disagreement and later observations

When an owner disagrees with a repair, record their account in their own words and review it against the agreed work, just as you reviewed the contractor's report. Then record what the team decided, why, and what route the owner has next under your process.

Formal warranty processes also rely on this kind of record. In Ontario, Tarion's conciliation guidance says a homeowner who considers a builder's repairs inadequate can provide supporting information such as photographs or an expert report. In British Columbia, BC Housing says that after repairs under home warranty insurance the homeowner receives the repair specifications and a letter confirming the completion date, and it advises keeping repair letters and inspection notes. These are local processes. Your team's review is not a warranty provider's decision.

Silence is not evidence that the owner is satisfied. If you have not heard back, record that you told them the outcome and when, not that they accepted the work. If the same problem appears after closure, keep the earlier case and its review: recording a repeat repair explains how to link the new attempt to the old one.

Use the checklist proportionately

Match the evidence to the work. A description and labelled photos can confirm a visible replacement such as a cupboard front, though not how its door closes; a recurring problem needs more. Asking for the same heavy pack on every job slows small repairs without making larger ones any safer.

  • Can we tell which case, home and location this is?
  • Do we know what work was agreed, including any change?
  • Does the evidence answer the review question for this work?
  • Is anything outstanding, limited or still uncertain, and is it written down?
  • Have we recorded who reviewed it, when and what they decided?
  • Does the owner know the outcome and any next step?

Collect only what the decision needs. Photos taken in an occupied home can show belongings and people, so ask for the work area only and keep the record within your team's normal access. A ticked checklist records that someone looked; it is not technical certification. The method works the same in a spreadsheet or any portal.

Where this applies

For customer care and warranty teams at residential developers who review contractors' work on individual defects after handover. The method fits any market and any tool. It does not cover building-control completion certificates or project close-out. The checklist is Toveta's proposed working aid, not a technical standard or legal test: check your contractual and statutory obligations, and any warranty provider's process, with your adviser.

About the author · Toveta

Has built software for property developers since 2016, from CRM systems to listing portals.

Sources

  1. Tarion. Conciliation process, assessment & resolution. Ontario, Canada; homeowner warranty process context only, checked 3 November 2026
  2. BC Housing. Home Warranty Insurance Claims. British Columbia, Canada; home warranty insurance claims only, checked 3 November 2026

Spotted an error or an outdated source? Email info@wisemonks.com and we will correct the page.

Frequently asked questions

Are before-and-after photographs enough?

They are enough when the question is about something visible, such as whether the right cupboard front was replaced. They cannot show how something works, what is behind a surface or whether the cause of a recurring problem has been dealt with. For that, ask the contractor or a qualified person what assessment the work needs.

Who should close the case?

Your customer care team, after it has recorded its review. The contractor reports the work complete; closing the case is the team's decision, made by a named person on a recorded date. In Toveta, a contractor submits completed work for review and the care team decides whether to close the case.

What if the homeowner disagrees with the repair?

Record what they observed in their own words, review it against the agreed work and tell them what the team decided and why. Closing a case records your team's decision; it does not end the owner's rights under their contract or any warranty process.

Can a case close with work outstanding?

Only if the record says so plainly: what was done, what remains and why the case is closing, for example because the remaining item now has its own case. Do not describe unfinished work as repaired.

Choose what Toveta may use on this device. You can come back and change this at any time. The cookie policy lists each cookie.

NecessaryLoads the site securely and remembers this choice.
Always on
AnalyticsGoogle Analytics 4. Shows us how the site is used.
AdvertisingLinkedIn Insight Tag. Measures our LinkedIn campaigns.