Changing contractors with open defects: a handover checklist
When another contractor takes over unfinished aftercare work, each open case has to move with its history intact. Here is what a residential care team should pass on, keep back and tell the homeowner.
Short answer
Before a new contractor takes over an open defect, give them a transfer record for that case: the current condition, the work already done, the agreed scope, the evidence, what is still unknown and the next action. Name the person responsible for that action and record whether the incoming contractor has accepted it. This guide assumes the change has already been decided through your commercial process. It does not cover termination, payment or warranty liability.
Establish the current position before transferring work
Before sending anything, find out where each open case stands. Start from your defect register, list the cases still assigned to the outgoing contractor and check each one:
- Is the case still open, and what is its next action?
- What work was carried out, and is there a record or photo of it?
- Did your team review that work, and what did it decide?
- Is any part of the scope disputed or still awaiting agreement?
- What information is missing, such as materials ordered or tests already done?
Record the position at transfer with the date and the name of the person who compiled it. Mark where each statement comes from: checked by your team, reported by the outgoing contractor or observed by the homeowner.
“Unknown” is a useful answer. If nobody knows whether parts were ordered or what an earlier visit found, record it as unknown and turn it into a question rather than a guess.
Assemble the open-case transfer record
Prepare one transfer record per open case, with a covering list if several cases move at once. Reuse the register’s case reference: the register stays the parent record.
What the incoming contractor needs
| Section | What to include |
|---|---|
| Identity | Case and location, outgoing and incoming contractor, care-team contact, transfer date. |
| Current condition | Original observation, latest reported condition, previous assessment and its author, date checked. |
| Work history | Agreed work, earlier visits, evidence references, review decisions, outstanding items. |
| Transfer scope | Work or assessment now requested, scope awaiting agreement, required documents, materials status if known. |
| Arrangements | Relevant access needs, any agreed appointment, people to notify. |
| Responsibility | Person responsible for the next action, the incoming contractor’s response, open questions, next update date. |
| Sharing record | Documents shared, recipients and dates, internal material kept separately. |
What stays with the care team
- Commercial discussion about the change, including prices and disputes.
- Personal information the work does not need.
- Internal notes and records about other homes or other contractors.
- Speculation about why earlier work did not finish. If the reason matters, record it in one neutral sentence.
Confirm responsibility for the next action
Assigning a case does not mean the new contractor has taken it on. Record each step separately, so everyone can see whether the brief awaits a reply or a visit is arranged.
| Step | What it means | What to record |
|---|---|---|
| Assigned | Your team names the incoming contractor as responsible for the next action. | Date and the person who assigned it. |
| Brief received | The contractor has the transfer record and the documents it lists. | Date sent, recipient and confirmation of receipt. |
| Accepted | The contractor agrees to take the next action. A reply with questions is not yet acceptance. | Date, the response and any questions raised. |
| Visit agreed | A date and access are arranged with the homeowner. | The appointment and who will attend. |
Until the contractor accepts the next action, your team remains responsible for follow-up. List each open question with the person who will answer it and a date. The aftercare process guide describes the normal assignment step; a contractor change repeats it with more history attached.
Whole-building handovers raise the same issue: RIBA’s Plan for Use Guide asks teams to check that responsibilities were properly handed over, and notes that clients often fail to separate operation, defects, routine maintenance and aftercare.
Work through a fictional contractor change
This cupboard repair has an incomplete visit record, so the incoming contractor assesses before anyone agrees a repair.
Fictional example
Hall cupboard repair passed to a new contractor
EX-H01Example development · Example home 18 · Hall cupboard
Earlier history
- 12 SepOwner reports that the hall cupboard door has dropped and no longer closes.
- 16 SepCare team assigns the case to Contractor A to inspect and adjust.
- 30 SepContractor A records a visit: hinges adjusted, further work may be needed. No completion photo and no note of what remains.
Position at transfer
- 20 OctThe commercial process confirms that Contractor B will take over Contractor A’s open cases.
- 21 OctOwner sends two current photos: the door still catches at the top.
- 21 OctCare coordinator compiles the transfer record. Unknown: whether replacement hinges were ordered and what Contractor A found in the frame.
Next action
- 22 OctCase assigned to Contractor B to assess the current condition. Transfer record and photos sent.
- 23 OctContractor B accepts the assessment and asks for the cupboard’s fitting specification.
- 24 OctAssessment visit agreed with the owner for 29 October, morning.
Fictional example. The home, dates and contractors illustrate the process. No repair outcome is shown because the assessment has not yet taken place.
The record does not suggest that Contractor A acted improperly or that Contractor B accepts the earlier work. The two unknowns stay open for the assessment. The second row below shows a case briefed but not yet accepted.
Open-case transfer record
One row per open case, with the reference from your defect register. Use it in a spreadsheet or copy the fields into your existing system, and send the incoming contractor only their rows. The fictional rows show one case accepted and one awaiting a reply.
| Case reference | Home and location | Outgoing / incoming contractor | Care-team contact | Transfer date | Original observation | Latest condition (source, date) | Previous work (recorded by) | Evidence and review decisions | Work now requested | Unknowns and open questions | Access and appointment | Next action (responsible) | Incoming contractor’s response | Next update to homeowner | Shared (what, with whom, when) and access review |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| EX-H01 | Example home 18 · Hall cupboard | Contractor A / Contractor B | Care coordinator | 21 Oct 2026 | Cupboard door has dropped and does not close (owner, 12 Sep) | Door still catches at the top (owner photos, 21 Oct) | Hinges adjusted, further work may be needed (Contractor A, visit 30 Sep) | Visit note only; no completion photo; no review decision | Assess the current condition and propose a repair; repair scope not yet agreed | Were replacement hinges ordered? What did Contractor A find in the frame? | Owner provides access; visit agreed 29 Oct, morning | Contractor B to assess; care coordinator to review the proposal | Accepted the assessment 23 Oct; asked for the fitting specification | 31 Oct | Report, visit note and photos to Contractor B, 22 Oct; internal notes kept separately; Contractor A’s access reviewed 22 Oct |
| EX-H02 | Example home 22 · Bathroom | Contractor A / Contractor B | Care coordinator | 21 Oct 2026 | Gap in the sealant around the shower tray (owner, 3 Oct) | Not rechecked since 3 Oct | None; no visit yet | Owner photos only | Assess and reseal if the tray is sound | Does the tray move? Unknown until assessed | Visit not yet agreed | Care coordinator to follow up with Contractor B on acceptance and a visit date | Brief sent 22 Oct; no reply yet | 28 Oct | Report and photos to Contractor B, 22 Oct; Contractor A’s access reviewed 22 Oct |
Scroll sideways to see every column.
Mark where each statement comes from: your team, the outgoing contractor or the homeowner. Write “Unknown” rather than guessing, and add the question it raises.
Tell the homeowner what changes
The homeowner should hear about the change from your team and not have to explain the defect again. Tell them:
- Their contact stays with your care team.
- Who will do the next step, once the incoming contractor has confirmed.
- What that step is: an assessment, a repair or a request for information.
- The visit date, only if it has been agreed.
- When they will next hear from you.
Leave the commercial reason out. If the next step is uncertain, see what to tell a homeowner when the repair date is unknown.
Review access and retain the history
Share only what the incoming contractor needs, and keep the full history with your team.
- Send only their cases and the documents each one needs.
- Save an extract as a separate file. A filtered view of the full register still contains its other rows.
- Review the outgoing contractor’s access to shared folders or portals when the assignment changes, keeping only what any remaining obligations need.
- Keep earlier visits, reports and review decisions in the parent record; do not overwrite them.
- Note in the sharing record what was sent, to whom and when.
Changing the contractor does not close the case or settle what happened to the earlier work. When Contractor B reports the work done, your team reviews it against the transfer record, using the completion evidence checklist. If you use aftercare software, check that reassignment keeps earlier entries visible.
Where this applies
For care teams at residential developers, in any market, once the decision to change contractor has been made. The record is an operating aid, not a legal standard. Whether a change affects warranty responsibility, payment or the previous contract depends on your agreements and local rules: check them with your adviser. Some warranty schemes have their own route for unresolved items. In Ontario, for example, Tarion’s conciliation process can in rare cases arrange for a third party to carry out repairs. Follow the procedure that applies to you.
Sources
- RIBA. RIBA Plan for Use Guide. UK, 2021; Stage 6 whole-building handover guidance, not a procedure for changing an aftercare contractor
- Tarion. Conciliation process, assessment & resolution. Ontario; process context only, checked 3 November 2026
Spotted an error or an outdated source? Email info@wisemonks.com and we will correct the page.